December Update for Sewage Treatment Works

Thames Water say that their improvement works at the Chesham site have been proceeding extremely well. They are currently investigating the recent increase in noise from the sewage treatment works site and are temporarily insulating some of their newly installed pipes. This should help reduce the noise until a permanent solution is put in place. 

Work so far:
- some old, redundant equipment has been removed for safe disposal, more efficient plant has been installed and is operating well
- Tank cleaning works are continuing and on-going
- new kiosks have been installed
- flood control work started 4th December
- ground work completed ready for electrical installation
- concrete paths and hard standing areas to be created in January

When work is carried out:
Thames Water is on target to complete the improvement works in March 2018. Their working hours are Monday to Friday 7.30am to 5pm. However, improvements works will stop over the Christmas period from Friday 22nd December until Tuesday 2nd January. 
 
If you have any questions or concerns about the works, get in touch with Thames Water on 0800 316 9800, select option two and quote reference BB970397.